Thursday 25 April 2024
Select a region
News

CI cable link with France fixed

CI cable link with France fixed

Tuesday 27 November 2018

CI cable link with France fixed

Tuesday 27 November 2018


Nearly two months on from the latest island-wide power cut, Guernsey Electricity has said work to repair the damaged cable link with France, via Jersey, has gone so well that the cable was fixed ahead of schedule.

The utility firm's Chief Operating Officer said tests have also been done to ensure everything is working properly, which it is.

Sally-Ann David, said: "Repair jointing undertaken by the cable manufacturer’s sub-contractor, NKT, was completed late last week. Over the weekend our engineers concluded cable testing and recommissioned the Barker’s Quarry transformer in Guernsey, prior to energising the cable.  On-going monitoring of the cable link will continue before it is returned to full service later this week and the on-Island generation plant will continue to be run to meet any additional seasonal demand requirements."

Bridge Harbour Power station

Pictured: The power station.

Ms David said a lot of work had gone into repairing the fault, which had happened during the tea time rush hour on Monday 1 October, causing short term traffic problems and other issues, with a few longer term faults including some damaged traffic lights. 

At the time, Guernsey Electricity's engineers worked quickly to restore power, after the fall first occurred at 16:52. The engineers started to restore power by 17:16 with all supplies back on by 17:34.

While initially they did not know what had caused the fault, it was quickly confirmed that the issue was on the Jersey side of the cable link with France, with the problem found to have occurred at Greve de L'ecq.

Greve_de_Lecq.JPG

Pictured: The scene of the fault in Jersey, which had caused an island wide power cut in Guernsey. 

The repair work had started by the first week in November and is now finished, with Ms David thanking staff in both islands.

"Guernsey Electricity is grateful to all employees and contractors involved in the complex repair project, including our colleagues at Jersey Electricity and the Jersey authorities.  In addition, Guernsey Electricity extends thanks and appreciation to our power station neighbours and customers for their patience and understanding throughout the repair process."

Since the power cut on Monday 1 October, Guernsey Electricity has generated all electricity on-island, which it said means just under 6000 tonnes of fuel oil was used in just one month to meet the island’s demand for electricity during the first few weeks. 

At the time the fault occurred, Guernsey Electricity's Head of Asset Management, Stuart Blondel, said "The cable link fault again reinforces the need for Guernsey to have a second subsea electricity cable connection to the island. This will allow us to achieve our aim of providing a secure, sustainable, affordable and low carbon electricity supply. Guernsey Electricity continues to progress discussions on the potential second cable connection direct to France."

There has been no update on those talks yet.

Pictured top: The scene of the fault in Jersey.  

Sign up to newsletter

 

Comments

Comments on this story express the views of the commentator only, not Bailiwick Publishing. We are unable to guarantee the accuracy of any of those comments.

You have landed on the Bailiwick Express website, however it appears you are based in . Would you like to stay on the site, or visit the site?